Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the December 2024 Project Management Oversight report. 

i

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Toggle Agency Project Title Asset Category Mode 2025 Funding 2025-2029 Funding Status
+ Metra Cybersecurity Systems N/A Rail $400,000 $1,600,000 Ahead of Schedul

Project Details

Description
This project covers all cybersecurity-related hardware, software, professional services, and cloud investments for the entire agency. The project also includes the purchase of hardware and software for multiple networks and segments including IT systems, positive train control (PTC), SCADA infrastructure, signal, telecom, and camera networks. The purchased equipment will cover vulnerability scanning and prioritization, patch automation and remediation, Security Information and Event Management (SIEM), and endpoint detection and response (EDR).This project will fund the purchase and installation of equipment and software for scanning, prioritization, and remediation of vulnerabilities. This also includes the purchase of hardware and software for multiple networks and segments including IT systems, positive train control (PTC), SCADA infrastructure, and signal, telecom, and camera networks. The purchased equipment will cover vulnerability scanning and prioritization, patch automation and remediation, Security Information and Event Management (SIEM), and endpoint detection and response (EDR).
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $400,000 $1,200,000 $1,600,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,200,000 $400,000 $1,200,000 $2,800,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,246,742
On Budget
Ahead of Schedul

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Contracts for cybersecurity and vulnerability software were awarded and software installation completed for 13 contracts. Contracts were awarded for vulnerability assessment. Software implementation was completed during this reporting period. This will be the final update on this project.

Last Updated 06.10.2025

+ Metra Ties & Ballast UPR Track & Structure Rail $200,000 $1,200,000 On Schedule

Project Details

Description
Metra’s Union Pacific North (UP-N) Line will undergo significant rehabilitation in 2022. Union Pacific Railroad’s crews will replace ties, clean or replace ballast, and replace switch components on the northern extents of the UP-N Line. This project improves the riding quality of the trains and reduces the incidence of slow orders, which can impact the ability to maintain on-time performance. Metra provides funds to improve the track along the UP-N Line and other lines and yard facilities owned by the Union Pacific Railroad.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $200,000 $1,000,000 $1,200,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $18,487,855 $200,000 $1,000,000 $19,687,855

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$30,178,736
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra coordinated efforts with UP Forces for work on the Kenosha Sub tracks 1 & 2 related to replacing and cleaning ties, replacement of ballast, as well as switch components from Mile Post (MP) 8.5 to MP 52.1. This work was complete during this reporting period. Work continues and additional locations were added to the project. Kenosha ties work to follow Harvard MP .75 to MP 62 and are expected to begin in late Spring 2025.

Last Updated 06.10.2025

+ Metra 16th St. Interlocker Electrical, Signal & Communications Rail $0 $0 On Schedule

Project Details

Description
This project will replace the 16th Street interlocking with a modern solid-state automated electronic system at a junction with tracks owned by Canadian National (CN) near 16th Street in Chicago. The 16th Street interlocking plant consists of an obsolete manual interlocking with two outdated hand lever machines built in 1901 and 1929. There are no manufacturers of spare or replacement equipment for these machines.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $69,590,000 $0 $0 $69,590,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$72,052,681
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The preliminary design was completed, and CN is waiting on drawings. Bid package documents were developed and design proposals were submitted. The award for the interlocking track and signal upgrades were awarded in October 2022 and activities for signal upgrades design continue. New grants were awarded for this project to address the capital needs for this project.

Last Updated 06.10.2025

+ Metra 47th ST Yard Improvements - Heating Support Facilities & Equipment Rail $0 $0 Ahead of Schedul

Project Details

Description
This project will replace the heating system for two facility buildings at the 47th Street Yard. The project scope includes the procurement and installation of boilers, piping, fixtures, and other equipment for the Diesel and Car maintenance shops.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$6,465,299
On Budget
Ahead of Schedul

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The work for the diesel shop construction, the 12KV distribution system, and sprinkler system reached substantial completion. The work for the Blue Island Yard had the canopy delivered and force account completed installation. Funds are fully expended and this project reached substantial completion. This will be the final update on this project.

Last Updated 06.10.2025

+ Metra 59th/60th ST. Station (U. of Chicago) Stations & Passenger Facilities Rail $0 $0 Behind Schedule

Project Details

Description
This project consists of the complete rehabilitation of the 59th/60th Street (U. of Chicago) station facility in Chicago along the Metra Electric Line. As part of the project, the 60th Street entrance will be reopened. Additional project elements include, but may not be limited to, lighting, sidewalk, bike facilities, landscape enhancements and other related work. The project will leverage $2,500,000 from the University of Chicago.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $69,600,000 $0 $0 $69,600,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$72,100,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for this project started in 2019 and the initial 60% design was completed in July of 2020. At that time the design was paused for the Section 106 National Environmental Policy Act (NEPA) and National Historic Preservation Act (NHPA) process. These activities have been completed and the design process re-started. Additional scope was added to the project based on the comments that came out of the Section 106 consultation process. The designer has submitted a 60% design and is progressing to 70%. The comments from the 60% design will be addressed in the 70% design submittal.

Last Updated 06.10.2025

+ Metra 95th Street Station CSU Stations & Passenger Facilities Rail $0 $0 Behind Schedule

Project Details

Description
This project will fund the rehabilitation of the 95th Street / Chicago State University Station on the Metra Electric Line in Chicago. The project elements may include the replacement and/or rehabilitation of station platforms, new lighting, rehabilitation of the headhouse, repair or replacement of roofs, installation of warming shelters, new platform amenities, and other related work. The project may also include wayfinding signage or other station identifiers. A new tunnel entrance will be added and parking facility upgrades will be completed. The station will be made fully accessible with the addition of elevators.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $48,000,000 $0 $0 $48,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$56,000,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The demolition of the existing telephone exchange building has been completed, and the debris has been taken off site. Construction fencing has been installed to ensure safety on the project site. The permitting process for the construction of this project is ongoing.

Last Updated 06.10.2025

+ Metra 111th St. Station / Pullman Stations & Passenger Facilities Rail $0 $0 Behind Schedule

Project Details

Description
This project will fund the rehabilitation of the 111th Street / Pullman Station on the Metra Electric District Line in Chicago. The project elements may include the replacement and/or rehabilitation ofstation platforms, new lighting, gatehouse/head house rehabilitation, replacement of leaking roofs, installation of new warming shelters, new platform amenities, and other related work. The project mayalso include wayfinding signage or other station identifiers.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $20,750,000 $0 $0 $20,750,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$20,750,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The National Environmental Policy Act (NEPA) and the State Historic Preservation Office (SHPO) review process has been completed. Metra is in the final stages of the procurement process for the designer to take the design from 30% to final design.

Last Updated 06.10.2025

+ Metra 147th St. - Sibley Station Stations & Passenger Facilities Rail $0 $0 Behind Schedule

Project Details

Description
This project consists of the complete rehabilitation of the 147th St. (Sibley Blvd.) station facility in Harvey along with the Metra Electric (ME) Line in Harvey. The project scope includes renovation of the station entrance, heated warming shelters, a canopy over half of the platform. Additional project elements include, but may not be limited to, lighting, sidewalk, bike facilities, landscape enhancements, and other related work.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $20,000,000 $0 $0 $20,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$20,938,354
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The construction at this station reached substantial completion in October 2024. Metra held a formal station opening ceremony on October 29. Final invoicing and close out activities are in progress. This is the final report on this project.

Last Updated 06.10.2025

+ Pace 2020 - Bus Stop Shelters, Benches, Pads & Signs Stations & Passenger Facilities Bus $0 $0 Behind Schedule

Project Details

Description
Engineering drawings, manufacture, and installation of bus stop shelters, concrete pads, and benches, including a heated bus shelter at the Waukegan Metra station.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,550,000 $0 $0 $1,550,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,550,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Activities continued by working with the vendor and received the first half of deliveries of shelters for the order placed in 2024. The new concrete pads contract was awarded and Pace is working with the vendor to acquire permits for the various locations.

Last Updated 06.10.2025

+ Pace 2020 - Bus Tracker Signs Stations & Passenger Facilities Bus $0 $0 On Schedule

Project Details

Description
Production of new electric signs and associated installation costs to provide real-time bus information to riders. In 2021, ten will be replacements for Pulse Milwaukee Line vertical markers, while an additional ten will be for new locations.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $750,000 $0 $0 $750,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$750,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Activity for this project continued in this reporting period with real time bus information signage and electrical connections installed. Additional signs will be installed using other PAYGO funding for additional signs. This will be the final update on this project.

Last Updated 06.22.2023