Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the June 2023 Project Management Oversight report

i

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Asset Category Mode 2025 Funding 2025-2029 Funding Status
+ CTA 5000 Series Rail Car Quarter Life Overhaul Rolling Stock Rail $0 $1,899,057 On Schedule

Project Details

Description
5000 Series Qtr. Overhaul - 714 Cars - The scope of this project is to provide for the Quarter?Life Overhaul on the 5000?Series rail cars. Schedule maintenance will include major component rebuilds and needed repairs to the car bodies. Additional work may include: replacing control groups, air conditioning units, truck assemblies, including traction motors, cables, batteries, brake calipers, axle assemblies, interior seat modification and other critical components based on condition assessment.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
$1,899,057 $1,899,057
Total $333,702,915 $0 $1,899,057 $335,601,972

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$400,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
As of the beginning of September, 490 out of 714 cars have completed the overhaul process. CTA continues to receive material kits and overhaul cars. On average, CTA forces are overhauling 14 rail cars per month but will start slowing down to 10 per month by end of the year.

Last Updated 12.19.2024

+ Metra A-20 (Techny) Interlocker Electrical, Signal & Communications Rail $0 $35,814,871 On Schedule

Project Details

Description
This project provides engineering and construction funds to modernize the A-20 Interlocking near Techny Road in Northbrook on the Milwaukee District North Line. The scope of work includes improving two grade crossings (Shermer and Techny Road), modernizing signals, and improving track between the Morton Grove Station and Deerfield Station. Under this project, work may include adding rail, switches, signals, crossovers, and renewal of track and signal circuits and cables. The project will implement a signal control system that is PTC compatible.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $35,814,871 $35,814,871
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $14,690,000 $0 $35,814,871 $50,504,871

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$19,258,610
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Preliminary engineering work is near completion and a construction Invitation for Bid (IFB) package is ongoing. Once completed, it will be submitted and advertised after the railroad cost sharing agreement is executed and potential grants are awarded.

Last Updated 12.19.2024

+ ADA Technology Upgrades and Transfer Centers Systemwide Bus $0 $0 On Schedule

Project Details

Description
Regional ADA Paratransit Communication Technology and Transfer Locations - Projects include upgrades to the Trapeze software, TripCheck online booking and tracking, TripCheck Interactive Voice Response phone system, text/email notifications, and Ventra integration. In areas with frequent transfers, funding will be used to purchase land, build facilities, and provide amenities for riders. Pace has identified a location that is adjacent to the Northwest Transportation Center in Schaumburg that is planned to be the first of these transfer locations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $20,000,000 $0 $0 $20,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$20,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Construction at the Northwest Transportation Center ADA Transfer Facility is ongoing. The contractor completed the underground sewer and drainage structure installation. Site work is ongoing with sandblasting of the existing bus bays and painting. Construction of the transfer facility included building the walls, slab-on-grade floor, transfer facility utilities, new bus driveway pavement, light pole foundations, curb and gutter. Progress continues on the implementation of various technology enhancement projects. The first two phases of the Taxi Access Program have been completed and the vendor is currently working on the third phase. Activity continues on two phases of Trapeze technology enhancements to Pace’s Trapeze paratransit scheduling system.

Last Updated 09.25.2024

+ CTA All Station Accessibility Program & Canopies at Montrose Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
This job order will provide for the design/construction of two new elevators at the Montrose Blue Line Station. Further this project will fund replacement of canopies at Montrose station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $31,021,197 $0 $0 $31,021,197

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$24,918,224
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project is in the design phase. The 60% design has been submitted to CTA. Design documents have been submitted to the State Historic Preservation Office (SHPO) for review and approval.

Last Updated 06.10.2024

+ CTA All Station Accessibility Program - Austin Station Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
Rehabilitate Rail Stations - ASAP (AUSTIN): This project is part of CTA’s All Stations Accessibility Program (ASAP). The goal of ASAP is to create a vertically accessible rail system within 20 years. ASAP also adds accessibility features to vertically inaccessible stations such as sidewalks and crosswalks, power-assisted doors, accessible fare array, braille and signage, accessible Customer Assistance (CA) kiosks and staff toilet rooms, enhanced lighting as appropriate, and expanded platform clearances for wheelchair maneuverability.This project is to improve the vertical accessibility at the Lake Line Austin station (Austin station). The original street level station opened on April 15, 1899 as a section of the “Lake Street Elevated Railroad’s” surface level extension. The current stationhouse was rebuilt in 1962 as part of the project that moved the western end of the Lake Street line from a street level alignment to an abandoned strip of the parallel “Chicago and Northwestern Railway” embankment. The Lake Line began using this elevated right-of-way on the CN&W (today’s Union Pacific) embankment between Laramie and Harlem on Sunday, October 28, 1962. This station has not been upgraded since it was rebuilt. The Austin station has been identified as a station that is not vertically accessible for all customers and will require the installation of an elevator to serve this center platform configuration. Work on this project will also bring elements of the station up to current Chicago Building Code requirements and meet the National Fire Protection Association (NFPA) 130 Standard for Fixed Guideway Transit and Passenger Rail Systems emergency egress requirements.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $26,064,000 $0 $0 $26,064,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$22,067,715
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for this project has been completed. CTA executed a contract for construction. The contractor is currently working on submittals and permitting.

Last Updated 12.19.2024

+ CTA All Station Accessibility Program - California Station Stations & Passenger Facilities Rail $0 $0 Behind Schedule

Project Details

Description
This project with provide for the renovation and expansion of the California Station. It will include a new platform, new emergency exist stairs and two new elevators. The station will be 100% ADA accessible. In addition, state of good repair work will be performed as part of the station renovation.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $36,000,000 $0 $0 $36,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$36,060,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The project is currently in the design phase. The 100% design has been submitted and is currently under review by CTA. The State Historic Preservation Office (SHPO) approved the design. CTA is working on acquisition of three properties required for the construction of this project.

Last Updated 06.10.2024

+ CTA All Station Accessibility Program - Elevator Replacement Stations & Passenger Facilities Rail $0 $27,100,000 Behind Schedule

Project Details

Description
CTA developed the Elevator Replacement Program to strategically maintain existing passenger elevators across the rail system as vertical accessibility is expanded via ASAP. The Elevator Replacement Program will rehabilitate or replace existing passenger elevators throughout the CTA rail system to reduce the backlog of elevator rehabilitation and replacement needs and bring them into a state of good repair. Current funded phase I provides for the replacement of betweenn 16 to 20 elevators and phase II provides for additional 16-20 elevators.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $27,100,000 $27,100,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $36,955,000 $0 $27,100,000 $64,055,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$34,855,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The designer completed site assessments and elevator inspections. An assessment report to prioritize the elevator replacement and rehabilitation locations has been developed. The report also provides the scope of work needed for each individual elevator. CTA is working with the designer to put together construction packages based on the priority recommendations from the assessment report to start the Task Order procurement process.

Last Updated 12.19.2024

+ Metra Auburn Park New Station Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
The new station in the Auburn Park neighborhood of Chicago will feature a platform-length canopy and heated headhouse with two elevators. The station will include a center boarding platform with a staircase down to street level entrance tunnel, a landscaped plaza with benches, canopy, bicycle parking, and a vendor space Metra will lease. A parking lot will include 79 parking stalls, 5 ADA parking spaces, and a passenger drop-off lane. The new station will be fully ADA accessible.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $18,400,000 $0 $0 $18,400,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$33,178,767
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The construction activities are in progress. The contractor completed the vendor building walls and Union Ave curb, sidewalk, and ADA ramps. In addition to that, the ongoing work includes the retaining wall and bridge deck waterproofing as well as demolition to prepare for the elevated station and the underground electrical installation.

Last Updated 12.19.2024

+ Metra Bicycle Parking Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
Metra was awarded CMAQ grants for the purchase and installation of bicycle parking facilities at stations across the system. Specific locations are to be determined
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $467,500 $0 $0 $467,500

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$85,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra reached the 100% design submittal which is currently under review. Once the review is completed, any final comments will be addressed and Metra will proceed to develop the Invitation for Bid documents.

Last Updated 06.10.2024

+ CTA Blue Line O'Hare Branch Traction Power Improvements Track & Structure Rail $0 $0 On Schedule

Project Details

Description
Blue Line O'Hare Branch Traction Power Improvements GTT - Project will include targeted track repairs to remove existing slow zones on the Congress Branch of the Blue Line. CTA has identified traction power voltage drop issues along the Blue Line. Scope of work will include but not limited to the following elements: New infill substations, infill wayside energy storage systems, infill tie houses, third rail replacement, addition of auxiliary negative rail; work will be performed by an outside contractor. In addition project will aslo provide for the replacement of ties, track fasteners, footwalks, and incidental signal and traction power; this part of work will be performed by CTA Field Forces.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $12,405,159 $0 $0 $12,405,159

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$207,100,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor completed installation and testing of wayside signal equipment and all cutovers along the specific portion of the blue line. The project is considered substantially complete with the contractor performing punch list items. Final invoices remain and this will be the final update on this project.

Last Updated 06.22.2023