Planning Programs and Projects
This page allows users to search for projects from the RTA’s Planning Programs. Users can search for projects by name or keyword from the Search bar or the Filter pulldown menus.
Table results display summary information about each project. To view more details for a project, select the + icon to expand the view for additional information.
Year | Project Title | Program | Project Type | Project Partner | Budget | Funding Source(s) | Status | |||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
+ | Justice Transit Improvement Study | Community Planning | Transit Improvement Plan | Justice | $67,410 |
|
Completed | |||||||||
Project DetailsDescription
This project, completed in 2007, assessed the market for improved transit service in the Village.
Current Activities
The Village of Justice has installed sidewalks along 79th Street from 88th Avenue to Roberts Road, and on Roberts Road from 79th Street to 87th Street. Two new bus shelters, four new benches, and two crosswalks have been added to improve access to Pace buses along 79th Street. Additionally, the Village has applied for Safe Routes to Schools funds for additional sidewalk improvements.
Funding Amounts by Source
Last Updated 09.14.2017 |
||||||||||||||||
+ | Melrose Park Lake Street Transit Improvement Plan | Community Planning | Transit Improvement Plan | Melrose Park | $78,850 |
|
Completed | |||||||||
Project DetailsRelated Reports
Description
This project addressed transit and access improvements to support mixed use development along the Lake Street corridor from 9th Avenue to 25th Avenue. The corridor incorporates the adjacent Metra Union Pacific West Line and Pace bus routes.
Current Activities
The study was completed in January 2007. The RTA is monitoring progress and will offer implementation support as needed.
Funding Amounts by Source
Last Updated 02.28.2013 |
||||||||||||||||
+ | Mokena Transit-Oriented Development Plan | Community Planning | Transit-Oriented Development Plan | Mokena | $124,500 |
|
Completed | |||||||||
Project DetailsDescription
This project identified transit-oriented development opportunities for the downtown Mokena Metra Rock Island District station area.
Current Activities
After completing the plan in 2008 the Village has taken several implementation steps, including the establishment of a TIF District as well as instituting permit fee relief and grant programs
Mokena received a grant from the Federal Railroad Grade Protection Fund in April 2011 for signal improvements at the intersection of Wolf Road and the Metra tracks located just south of Front Street. This will help improve traffic movements across the Metra tracks at Wolf Road, as suggested in the Plan. Mokena was chosen as part of the 2012 RTA Community Planning Program of Projects for assistance connecting with development experts to discuss opportunities in the TOD study area. A panel of development experts met in November 2012 to discuss potential redevelopment opportunities in the TOD area and provide guidance and advice on ways the Village can attract development. A summary of this discussion can be found in the Study Documents. In recent years, (2) commercial projects were completed; 4,400 sq.ft 'Tribes Brewery' completed in May 2018, and 5,000 sq.ft 'Current Call Theater' completed in February 2017. Funding Amounts by Source
Last Updated 09.16.2019 |
||||||||||||||||
+ | Naperville Circulator Implementation Plan | Community Planning | Transit Improvement Plan | Naperville | $82,043 |
|
Completed | |||||||||
Project DetailsDescription
This project developed service specifications, potential funding sources and a marketing plan for a local transit circulator system in Naperville, as recommended in the DuPage Area Transit Plan. The final report was approved by the Naperville City Council on July 17, 2009.
Current Activities
Naperville has been exploring strategic funding opportunities since completion of this project with support from the RTA and Pace.
Funding Amounts by Source
Last Updated 10.05.2016 |
||||||||||||||||
+ | Orland Park LaGrange Road Transit Improvement Plan | Community Planning | Transit Improvement Plan | Orland Park | $99,855 |
|
Completed | |||||||||
Project DetailsDescription
This project identified transit and pedestrian friendly improvements for development/redevelopment along the heavily used LaGrange Road Corridor. The study area consisted of LaGrange Road from 131st Street to Interstate 80.
Current Activities
This plan was completed in April 2010. A $106 million IDOT project that was launched in the summer of 2011 includes widening LaGrange Road to three lanes in each direction from 131st to 179th streets. Construction also included brick paver crosswalks in key locations, (the first-ever brick paver crosswalk crossing a Federal/State roadway in the State), along with new sidewalks, landscaping and extensive ornate aesthetic enhancements to enhance pedestrian access and safety to the Metra station.
Funding Amounts by Source
Last Updated 06.13.2017 |
||||||||||||||||
+ | Villa Park Station Area Plan | Community Planning | Transit-Oriented Development Plan | Villa Park | $77,887 |
|
Completed | |||||||||
Project DetailsDescription
This Station area plan focused on transit-oriented development opportunities and improving multi-modal access to the Village's commuter rail station on the Metra Union Pacific West Line. Current Activities
The study was completed in November 2006. In 2010, the Village was awarded $900,000 through the Illinois Transportation Enhancement Program (ITEP) for streetscape enhancements to Ardmore Avenue. In July 2021, the Village Board voted to approve a proposed $120 million mixed-use apartment building northwest of the Villa Park Metra station. The seven-story, 348-unit complex is to be located on 1.69 acres of a block bounded by East Vermont Street on the north, North Beverly Avenue on the east, West Terrace Street to the south and North Ardmore Avenue to the west and will feature first floor retail space. The developer broke ground on the project in 2022. Funding Amounts by Source
Last Updated 11.09.2023 |
||||||||||||||||
+ | DuPage Phase I Community Circulators | Community Planning | Transit Improvement Plan | DuPage Mayors & Managers | $170,151 |
|
Completed | |||||||||
Project DetailsRelated Reports
Not Available Description
This study assessed and refined potential market areas identified in the DuPage Area Transit Plan (DATP) for circulator services and developed preliminary service specifications/characteristics. In addition, the study explored potential institutional arrangements that are a prerequisite to successful service deployment.
Circulator service designs were completed for four communities; Addison, Downers Grove, Lombard and Wheaton. Local task forces were formed to create an implementation plan for each community. Final implementation strategies were presented to each city council/village board with a resolution recommending financial and institutional commitment.
Funding Amounts by Source
Last Updated 08.08.2017 |
||||||||||||||||
+ | Harvey Intermodal Station Area Plan | Community Planning | Transit-Oriented Development Plan | Harvey | $83,693 |
|
Completed | |||||||||
Project DetailsDescription
This project provides a plan for redevelopment of the city's downtown area that includes the Metra Electric District commuter rail station and Pace's Harvey Transportation Center. The plan was completed in November, 2005.
Current Activities
In 2010, Pace funded a Transit Signal Priority Project for the Harvey Transportation Center. Testing of the full deployment of TSP was completed in August 2010. Twenty signalized intersections along 158th, Sibley Boulevard, Halsted and Park Avenue were deployed in Phase I, and in Phase II 10 signalized intersections were deployed along Halsted Street. This project helped to improve circulation and movement within the downtown area, as recommended in the plan.
Funding Amounts by Source
Last Updated 06.08.2017 |
||||||||||||||||
+ | Midlothian Station Area Enhancement | Community Planning | Transit-Oriented Development Plan | Midlothian | $140,000 |
|
Completed | |||||||||
Project DetailsDescription
The study produced a plan for the revitalization of the station area and surrounding commercial district. Previous Village planning studies were used as input to the plan. Current Activities
The study was completed in December 2005. In November 2012 the Village met with a panel of development experts to solicit guidance and advice on ways to capitalize on redevelopment opportunities in the TOD study area. A summary of this discussion can be found under Related Reports. In early 2019 the RTA applied for and was awarded CMAQ funding a second time on behalf of the Village to construct pedestrian access improvements for southern access to the Midlothian Metra station. Funding Amounts by Source
Last Updated 02.02.2023 |
||||||||||||||||
+ | Niles Bus Oriented-Development Plan for Milwaukee Avenue | Community Planning | Corridor Planning | Niles | $100,000 |
|
Completed | |||||||||
Project DetailsRelated Reports
Description
This plan explored transit oriented development opportunities along Milwaukee Avenue within the Village of Niles. The plan focused on strategies to improve transit facilities and services within the context of an overall effort to improve the function and aesthetics of the Milwaukee Avenue corridor. Improvements to transit facilities, new pedestrian amenities, streetscaping, traffic circulation, access to businesses, and potential redevelopment opportunities are major components addressed in the plan. Coordination with existing Pace service and the Niles Free Bus service was also explored. Current Activities
This project was initiated in March of 2005 and is now complete. The Niles Village Board approved the Milwaukee Avenue Plan on January 24, 2006. Funding Amounts by Source
Last Updated 07.28.2021 |