Year | Project Title | Program | Project Type | Project Partner | Budget | Funding Source(s) | Status | |||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
+ | Schaumburg Transit Service Assessment | Community Planning | Transit Improvement Plan | Schaumburg | $100,000 |
|
Completed | |||||||
Project DetailsRelated Reports
Description
This study created a Local Transit Improvement Plan for the Village. This was accomplished by reviewing the performance of existing transit services, determining customer satisfaction with the existing services, and developing coordination among existing services. Current Activities
The plan was accepted by the Village of Schaumburg Village Board on December 13, 2011. Since that time, the Village has taken several actions to implement the plan and improve transit service. Schaumburg worked with Pace to reroute the Woodfield Trolley (Route 905) to better serve riders and revised the funding formula to create savings that allowed an increase in service. Additionally, Pace Route 602, a Metra feeder service, was reroute to more densely populated areas in the hope of increasing ridership. This change went into effect in September of 2016. The Village has also made changes to its Dial-A-Ride Transportation that include additional service and greater availability of subscription service. Funding Amounts by Source
Last Updated 03.10.2022 |
||||||||||||||
+ | Southwest Will TMA Study | Community Planning | Transit Improvement Plan | Joliet Arsenal Development Authority | $125,000 |
|
Completed | |||||||
Project DetailsDescription
This study updated the Joliet Arsenal Development Authority's (JADA) transportation plan for the area in and around the former Joliet Arsenal. The study included an evaluation and feasibility study for the creation of a Transportation Management Association for southwest Will County. Current Activities
The study was completed in June, 2010. In July of 2011, an RFP was released and proposals sought for the Southwest Will TMA Implementation and Travel Demand Study by the Joliet Arsenal Development Study and the City of Joliet. A committee consisting of JADA, Will County, Will County Governmental League, Will County Center for Economic Development and the City of Joliet selected Ruettiger & Tonelli / AECOM after the interview process. The project commenced in the summer of 2013. Funding Amounts by Source
Last Updated 11.11.2020 |
||||||||||||||
+ | St. Charles Circulator Feasibility Study | Community Planning | Transit Improvement Plan | St. Charles | $99,285 |
|
Completed | |||||||
Project DetailsRelated Reports
Description
This project studied the feasibility of a circulator system between two transit-oriented developments (First Street and Towne Center) within St. Charles and the Geneva Metra Station.
Current Activities
The project was completed in August 2010 and the plan accepted by the City of St. Charles City Council on August 2, 2010.
As of December 12, 2011, Pace Route #802 has been re-routed and no longer provides service from Geneva to St. Charles. A new Call-n-Ride has been implemented (Route #592) with service to/from the Geneva Metra station and other locations. For more information please visit http://www.pacebus.com/sub/schedules/cnr_detail.asp?RouteNo=592. As of October 2013, the Call-n-Ride ridership averages around 3.32 riders per hour on weekdays, and 1.9 riders per hour on Saturdays. Funding Amounts by Source
Last Updated 01.04.2017 |
||||||||||||||
+ | Western Springs Downtown Plan | Community Planning | Transit-Oriented Development Plan | Western Springs | $119,980 |
|
Completed | |||||||
Project DetailsRelated Reports
Description
Called the "Queen Suburb of Chicago" by early realtors, Western Springs is known as a community with lovely homes, great neighborhoods, and a strong sense of community. It also has a wonderful, small downtown with unique restaurants and shops centered on a Metra commuter rail station. To maintain and enhance this unique core of community life, in 2011 the Village crafted a Downtown Redevelopment Plan. The planning process involved an extensive public participation process, including a community survey, participatory workshops, a temporary storefront office for walk-in conversations about downtown, direct interviews and meetings with property owners and developers, and oversight by a steering committee. The intensive process resulted in a Plan that was adopted by the Village Board on August 22 by Ordinance 11-2643 as an amendment to the Village's Comprehensive Plan. Highlights of the plan include a wayfinding system, a renovation strategy for the overall streetscape, identification of nine potential redevelopment sites, creation of design guidelines, façade renovation sketches, implementation strategies, a marketing and promotions strategy, and examination of parking demand and identification of parking improvements. Current Activities
Construction completed in 2020 of Foxford Station, a 28 unit condominium development with 3,800 square feet of ground-floor commercial space at Wolf Road and Burlington, across the street from the Metra station. A developer plans to break ground in the fall of 2022 on a 10-unit condominium development on Hillgrove Ave., between Franklin and Howard Avenues. The RTA will continue to monitor progress and offer assistance as needed. Funding Amounts by Source
Last Updated 10.25.2022 |
||||||||||||||
+ | Will County Coordinated Paratransit Study | Community Planning | Transit Improvement Plan | Will County | $99,995 |
|
Completed | |||||||
Project DetailsRelated Reports
Description
This study created a coordinated paratransit plan for the County. This included an inventory of existing paratransit services, a gap analysis based on the inventory, and identified strategies to begin the development of an action plan to implement a pilot program of a coordinated paratransit initiative.
Current Activities
The final plan was adopted by the Will County Board of Directors in November 2010 and the RTA worked with the County to implement the recommendations, including forming a Coordinated Paratransit Committee and identifying funding opportunities for a Mobility Manager.
In November 2011, the RTA Board approved funding through the Job Access Reverse Commute/New Freedom (JARC/NF) program for the Will County Mobility Management Program . This program will provide transportation and mobility management services for persons with disabilities, the elderly and low-income individuals residing in eastern Will County townships. Funding Amounts by Source
Last Updated 12.15.2016 |
||||||||||||||
+ | Wilmette Village Center Master Plan | Community Planning | Transit-Oriented Development Plan | Wilmette | $124,128 |
|
Completed | |||||||
Project DetailsDescription
In late 2009, the Village of Wilmette began a planning process that leveraged the Village's high commuter usage of the rail and bus systems to create a long-range vision for an improved downtown area. This ten-month planning and design process built upon several other studies and engaged some 300 residents in the process. The study process evaluated market feasibility, infrastructure capacity, and most importantly public opinion to create the final plan recommendations. The result of the project created a Master Plan that suggests increased densities, building heights and a mix of acceptable land uses combined with an appropriately regulated urban design and public realm character for defined portions or Target Areas of the Village Center. Additionally, the Master Plan conceptually addresses other areas of the Village Center, most notably the Green Bay Road corridor and future redevelopment which may occur there. The final Wilmette Village Center Master Plan is intended as a basis, or starting point, for any future detailed development planning, design or engineering that will be required leading up to construction and implementation of all or portions of the Plan. It is a guide and as an approved Village tool, it will provide the roadmap for future initiatives, Village leadership goal setting and budgeting and management of the downtown. It is a living document and must be easily and effectively managed and adaptable to changing market conditions. While the time horizon for this Master Plan has been identified as a 10 to 15 year program, it is important that staff and Village leadership update and benchmark the plan on a regular interval. The Village of Wilmette officially adopted the Village Center Master Plan document as an amendment to their comprehensive plan on January 25, 2011. The project's website contains detailed information and reports. Current Activities
In 2011, a CMAP-led Value Capture study looked at potential funding mechanisms and innovative financing techniques to identify ways for the Village to fund the parking deck recommended in the TOD plan. The Executive Summary of this study can be found here. In November of 2020 the Village of Wilmette gave final approval to a developer to construct a mixed-use building across from the Metra station at 1210 Central Avenue. There will be 109 apartments, ground floor commercial space, and 173 car parking spaces. Funding Amounts by Source
Last Updated 05.18.2021 |
||||||||||||||
+ | Addison Advantage Transit Improvements | Community Planning | Transit Improvement Plan | Addison | $100,000 |
|
Completed | |||||||
Project DetailsDescription
This project assisted the Village in identifying, analyzing, and developing a transit improvement plan to encourage, promote, and complement transportation options along Route 20/Lake Street. The study focused on Lake Street from Route 83 on the east to Swift Road on the west, taking into account Pace bus Routes 711 and 715. Redevelopment guidelines that support transit and pedestrians, and a circulation plan recommending ways to accommodate multimodal transportation throughout the corridor were prepared. This project was developed as a continuation of another RTAP Project, the DuPage Mayors and Managers DuPage Community Circulator Prototype Plan, of which the Village was a participant. Current Activities
This project was completed in July 2010. The plan was presented to and accepted by the Village of Addison Village Board on July 6, 2010. The Village is currently exploring funding options to install bus shelters along Lake Street at key Pace bus stops as recommended in the plan. Funding Amounts by Source
Last Updated 10.26.2020 |
||||||||||||||
+ | Chicago Heights Station Area Plan | Community Planning | Transit-Oriented Development Plan | Chicago Heights | $99,575 |
|
Completed | |||||||
Project DetailsDescription
This project examined potential pedestrian enhancements and transit-supportive land uses within the City's downtown which includes the Pace Chicago Heights bus terminal and a proposed site for a station on the SouthEast Service Line Extension. Current Activities
The plan was adopted by the City Council in November 2009. The plan recommends locating the station near the existing 17th Street Crossing and closing the 17th Street Crossing to provide for safe access to the station. Redevelopment of the area around the station includes mixed-use and condo and townhouse style housing. Funding Amounts by Source
Last Updated 06.08.2017 |
||||||||||||||
+ | Chicago Transit-Friendly Development at CTA Stations | Community Planning | Transit-Oriented Development Plan | Chicago | $250,000 |
|
Completed | |||||||
Project DetailsRelated Reports
Description
The City of Chicago, in conjunction with the Chicago Transit Authority (CTA), looked at three elevated train station areas (Berwyn on the Red Line, 43rd Street on the Green Line and a potential infill station near Cermak on the Green Line) and developed comprehensive land use (urban design) and transportation plans for each station. This study was an important first step in the citywide effort to strengthen the relationship between land use and transportation, plan for neighborhood growth and enhancement, inform future development and redevelopment decision-making, and guide public and private investment in three station areas. Current Activities
The new Cermak-McCormick Place Green Line Station, funded with $50 million in City TIF funds, opened for service in February 2015. A new entertainment district between McCormick Place and the station has been developing since 2015, including the new Wintrust Arena and four new hotels, three of which provide a connection via a skybridge to McCormick Place's west building. A 24-story, 275-unit building in the McCormick Square area and one block from the station wasa completed in 2020 and the same developer is seeking zoning approval to construct a 12-story apartment building immediately south of it, at Wabash and Cermak. Funding Amounts by Source
Last Updated 10.25.2022 |
||||||||||||||
+ | Evanston Multi-Modal Master Transportation Plan | Community Planning | Transit Improvement Plan | Evanston | $100,000 |
|
Completed | |||||||
Project DetailsRelated Reports
Description
The general scope of the project was to develop mode specific plans (transit, pedestrian, and auto) to compliment and integrate with the existing Evanston Bike Plan. The goal was to foster an integrated and coordinated transportation system throughout Evanston. The RTA participated in the transit component of this plan.
Current Activities
in late 2013 the City received CMAQ approval for a protected bike lane along Dodge Avenue from Church Street to Howard Street. This project will begin in 2014 and will improve access and safety for bicyclists throughout the downtown TOD area. For more information please visit http://www.cmap.illinois.gov/mobility/strategic-investment/cmaq. Additionally, the City was selected as part of the 2015 RTA Community Planning Program to explore ways to create a TOD Parking Policy throughout the City. The completed policy is expected to be adopted by the City Council in fall of 2016.
In fall of 2015, the City was awarded CMAQ funding to construct covered bicycle parking at the Main Street CTA and Metra stations through the RTA's Access to Transit Improvement Program. Funding Amounts by Source