River Grove Thatcher Avenue TOD

Description

This project developed a transit-oriented master plan for 2.16 acres of land located immediately adjacent to the Village's Metra station, building off recommendations in the Grand Avenue Village Center Plan completed in 2006. The plan also includes a market assessment of market-supportable densities and transit-supportive uses appropriate for this site and conceptual ideas for various other opportunity sites throughout the TOD area.

Current Activities

The plan was adopted on June 5, 2014. To continue support of their efforts, the RTA selected the Village to receive funding assistance for a Developer Panel as part of the 2015 Community Planning Program. The RTA, in conjunction with ULI convened a panel of development experts to provide guidance and advice to Village staff and elected officials on ways to attract investment in the TOD area. This discussion took place on November 18, 2015 and the summary report is available on the project's RTAMS webpage.

In 2021, the River Grove Station development was completed and began leasing units. The 40-unit multi-family development is located adjacent to the River Grove Metra station in the area designated as "Site 1" in the River Grove Thatcher Avenue Transit-Oriented Development Plan (2014).


Project Type
Transit-Oriented Development Plan
Project Year
Project Status
Completed
Grantee
River Grove
Planning Program
Community Planning
Funding Amounts by Source
Source Amount
RTA $60,000
Local $15,000