Plainfield Park and Ride Access Improvements

Description

The RTA is providing the Village of Plainfield Phase II engineering and construction funds to build a 0.6 mile extension of a 10' wide shared-use path along the south side of 143rd Street from Van Dyke Road to Wallin Drive. Wayfinding signage to the Plainfield Park-n-Ride and downtown Plainfield will be included along the route. These improvements will better connect residents to transit and downtown Plainfield. 

Current Activities

 Phase I review resubmittal package was submitted to IDOT for review.  Approval expected in December 2024.


Project Type
Pedestrian Access to Transit
Project Year
Project Status
In Progress
Grantee
Plainfield
Planning Program
Access to Transit Program
Funding Amounts by Source
Source Amount
Federal $737,432
Last Updated 10.11.2024